J. Cumby will be demolishing the existing aeration digester equipment on the site, such as 12" telescopic valves and 12" supernate ductile iron pipe.

J. Cumby will also be installing a new 12" decanter system, 12" and 6" decanter line, ductile iron pipe and pipe supports.

This site is set to be finished by 2023.

Project Information

  • Location: Gallatin, TN

  • Date Completed (Estimated): TBD

  • Contract Value of $99,000+

  • Owner: City Of Gallatin

  • Engineer: James C Hailey & Company

Notable Specs

  • This is one of the several sites that J. Cumby has had the privilege to work on for Gallatin.