Pump Station Rehabilitation

Major Activities:

- Replacement of existing pumps, piping, motors, motor shafts, valves, VFDs, control panels, generator

- Demolition, removal, installation and modifications of existing concrete

- Addition of odor control system

Notable Specs:

Pump station will be bypassed during replacement of pumps and other construction activities. This force main that feeds the pump station is the main feed of the Nissan Plant located in Smyrna Tennessee.

Location: Smyrna, TN

Date Completed (Estimated): October 2024

Contract Value: $4,271,000.00

Owner: Town of Smyrna

Engineer: Thomas and Hutton