1 Million Gallon Clearwell and New Pump Station. All associated yard piping, a new generator, and replacing existing HSPS control valves, existing filter backwash troughs, and venturi meter and vault.

Major Activities:

  • Demolition of existing clear well.

  • Excavation for 1MG Clearwell and Pump Station.

  • Demolition of existing yard piping.

PROJECT INFORMATION:

  • Location: Mooresville, NC

  • Date Completed (Estimated): September 16th, 2026

  • Contract Value of $8,043,000

  • Owner: Town of Mooresville, NC

  • Engineer: Willis Engineers